Planning & Projects Committee Meeting

August 6, 2007

 

 

Chairman Buddy Daisy called to order the Planning & Projects Committee Meeting of the Terrebonne Levee and Conservation District at 220 Clendenning Road, Houma, Louisiana, on August 6, 2007, immediately following the Finance Committee Meeting.

 

Upon roll call by Angela Rains, Commissioners recorded present were Mr. Alford, Mr. Talbot, Mr. Leward Henry, Mr. Willis Henry, Ms. Teuton, Mr. Moore, Ms. Dillard, Mr. Luke and Mr. Daisy.  

 

Under Public, Ms. Barbara Larpenter addressed the Board regarding a project presented by GSE, Inc. at the Parish Council Meeting.

 

Mr. Zeringue addressed the issues as noted by Ms. Larpenter under Public.

 

Mr. Gerald Chouest addressed the board regarding moving the choke at the ship channel north.

 

Mr. Reggie Bourg addressed the board regarding the Upper Ward 7 Levee Project. 

 

Under Executive Director’s Report, Mr. Zeringue asked the Board to consider authorizing Eustis’ revised cost estimate for additional geotechnical engineering services for Reach J-2 not to exceed $27,780.00.

 

Motion of Commissioner Willis Henry, seconded by Commissioner Talbot, motion carried, to authorize Eustis’ revised cost estimate for additional geotechnical engineering services for Reach J-2 not to exceed $27,780.00.

 

Mr. Zee asked the Board to approve Resolution 07-430 in Support of Wetland Sustainability within the Morganza to the Gulf Hurricane Protection Project.

 

Motion of Commissioner Leward Henry, with a unanimous second, to approve Resolution 07-430 in Support of Wetland Sustainability within the Morganza to the Gulf Hurricane Protection Project.

 

Mr. Zeringue reported on the status of WRDA in Washington, as well as the related Morganza to the Gulf Hurricane Protection Project. 

 

Field Superintendent Greg Gautreaux provided an update of in-house projects along Lower Ward 7 Levee.

 

Mr. Gautreaux asked the board for authorization to rent a track mounted crawler carrier from Quest Construction for the Lower Ward 7 Levee.  The costs for this rental will be cost shared with Terrebonne Parish Consolidated Government.

 

Motion of Commissioner Leward Henry, seconded by Willis Henry, motion carried, to authorize rental of a track mounted crawler carrier from Quest Construction for the Lower Ward 7 Levee work, with the cost to be shared with the TPCG.

 

Mr. Gautreaux also asked the board for authorization to purchase one bush hog tractor at the state contract price of $46,103.15.

 

Motion of Commissioner Talbot, seconded by Commissioner Leward Henry, motion carried, to authorize purchase of one (1) bush hog tractor at the State contract price of $46,103.15.

 

Keith Meyer with Evans-Graves Engineers, Inc. gave an update on the Pointe-Aux-Chenes Floodgate project.

 

Phil Schexnayder with GSE Associates, Inc. requested approval of balancing change order in the amount of $2,243.13 for the Montegut Structure and Levee Repair (TE-01) project.

 

Motion of Commissioner Willis Henry, seconded by Commissioner Leward Henry, motion carried, to approve Balancing Change Order in the amount of $2,243.13 for the Montegut Wetlands Structure and Levee Repair (TE-01) project.

 

Mr. Schexnayder reported on the Morganza to the Gulf Reach J Segment 2 Project.  A new contract to design a 10’ levee is currently under the consideration of the administration and will be presented to the Board with staff’s recommendations.

 

 

 

 

 

Planning & Projects Committee Meeting

August 6, 2007

Page Two

 

 

Mr. John Spiece with Morris Hebert, Inc. reported on the Lower Petit Caillou Levee Reconstruction Project (TE-07b).  Mr. Spiece reported on the Pointe-aux-Chenes Floodgate, as well as the status of the First Lift Levee System, MPH Task Order No. 4, Amendment No. 5.

 

Jeff Pena with Shaw Coastal, Inc. reported on the Barrier Plan Reach II. 

 

Mr. Pena requested Change Order No. 1 to Civil Construction contract for an additional time extension of 75 calendar days, and a reduction of $37,318.00.  Additionally, as part of the same motion, Mr. Pena requested the approval of Amendment No. 5 to Shaw Coastal’s engineering agreement for additional construction administration and inspection related to Civil’s time extension, with a not to exceed $58,585.00.

 

Motion of Commissioner Willis Henry, seconded by Commissioner Leward Henry, motion carried, to approve requested Change Order No. 1 to Civil Construction contract for an additional time extension of 75 calendar days, and a reduction of $37,318.00, and as part of the same motion, the Board approved Amendment No. 5 to Shaw Coastal’s Engineering agreement for additional construction administration and inspection related to Civil’s time extension, with a not to exceed $58,585.00. Commissoners Moore and Teuton voted against the motion.

 

Mr. Pena presented the Board with a slide presentation and update on Reach H-3 First Lift Project and the Permitting for Reach H-3.

 

Mr. Pena reported on the Lower Bayou Dularge Mitigation Plan Implementation.

 

David Boudreaux with T. Baker Smith, Inc. reported on the 4-3C West Forced Drainage Project.  The levee on the West side of the project is complete.

 

On the Ward 7 Levee Reconstruction Project, Contract 1 and 2 are both in clear lien period.  The contractor is currently performing items on the punch list.

 

On the Morganza Reach J-1 Levee, Mr. Boudreaux requested approval of Change Order No. 1 for 42 additional calendar days for the Segment A of Reach J-1 Levee.

 

Motion of Commissioner Willis Henry, seconded by Commissioner Talbot, motion carried, to approve Change Order No. 1 for 42 additional calendar days for Segment A of Reach J-1 Levee.

 

For the J-1 Floodwall, Mr. Boudreaux requested approval of a balancing Change Order No. 1 reducing the contract by $624,953.40.

 

Motion of Commissioner Talbot, seconded by Commissioner Alford, motion carried, to approve the balancing Change Order No. 1 reducing the contract for J-1 Floodwall by $624,953.40.

 

Mr. Boudreaux further requested the Board to terminate the construction contract with Lowland for the Reach J-1 Floodwall.

 

Motion of Commissioner Leward Henry, seconded by Commissioner Willis Henry, motion carried, to terminate the construction contract with Lowland for the Reach J-1 Floodwall.

 

On the MTG Program Management Services contract, TBS assisted the TLCD in coordinating a new task order for GCR for real estate activities related to Reach H-3 levee.  These real estate activities include updated title work, negotiations, appraisals and other matters.  TBS also assisted the Levee District in negotiating a cooperative agreement with the LADNR to acquire the necessary oyster leases for Reach H-3 Levee.

 

Under President’s Report, Mr. Alford spoke regarding the Council Committee meeting to review sinking a ship in the HNC.  Mr. Alford further discussed the goals and duties of the levee board.  He urged the board to stay focused. 

 

There being no further business to come before the Board, it was moved by Commissioner Leward Henry, seconded by Commissioner Moore, unanimously carried, to adjourn the August 6, 2007 Planning & Projects Committee Meeting of the Terrebonne Levee and Conservation District at 8:13 o’clock P.M.

 

 

 

___________________________                              _______________________

Walton Daisy, Chairman                                                Jerome Zeringue, Secretary