Chairman
Upon
roll call by
Under
Public wishing to address the Board, Reggie Bourg
addressed the Board regarding the Ward 7 horseshoe.
Under
Executive Director’s Report, Mr. Zeringue addressed the issue of pump
malfunction at the Humble Canal Floodgate.
Several options are under advisement to remedy the problem. Mr. Zeringue also provided the Board with an
update for the Morganza to the Gulf Project.
Motion
of Commissioner Talbot, seconded by Commissioner Moore, motion carried, to
approve Change Order No. 6 in the amount of $145,954.00 for the construction of
a 100’ steel bulkhead on the Montegut Wetlands Project (TE-01).
Mr.
Schexnayder reported on the Morganza to the Gulf
Reach J Segment 2 Project. GSE met with
the soils consultant. The project is
back on schedule.
Brian
Kendrick with MPH, Inc. reported on the Lower Petit Caillou
Levee Reconstruction Project (TE-07).
The Grillot/Bertucci construction contract is
complete, except for the final payment.
MPH is waiting on the TLCD to perform additional marsh creation. The final planting and monitoring plan will be
initiated upon completion of construction.
On
the Morganza to the Gulf PAC Reach J-1 project, all
tasks are complete with the exception of appraisals on tracts of land near the
marina. MPH is waiting on a map being
prepared by Evans-Graves Engineers, Inc.
Mr.
Thibodeaux asked the Board to authorize execution of the Mitigation Contract
with Gremillion Land Management Company in the amount
of $76,500.00 for the Ward 7 Levee.
Commissioner
Luke is noted as entering the proceedings at
Motion
of Commissioner Leward Henry, seconded by
Commissioner Alford, motion carried, to authorize the execution of the
Mitigation Contract with Gremillion Land Management
Company in the amount of $76,500.00 for the Ward 7 Levee.
Jim
Geihsler with SCI made a presentation to the Board on
the Ward 7 Levee Reconstruction Project.
Motion
of Commissioner Leward Henry, seconded by
Commissioner Alford, motion carried, to issue a Notice to Proceed for Civil
Construction Additive Alternate pertaining to earthen work along Bayou Neuff to Denbury site along the
Ward 7 Levee (pending appropriation of the rights of way).
On
the Reach H, Segment 3 First Lift (H-L-003), Gulf South Pipeline has submitted
a copy of the construction cost estimate and reimbursement agreement on
Planning & Projects Meeting
Page Two
On
Reach H-3 Permitting, landowner notice of mitigation options will expire on
Matt
Sevier with Shaw Coastal, Inc. reported to Board after conducting a Phase I
Environmental Site Assessment of the property located at
David
Boudreaux with T. Baker Smith, Inc. reported on the 4-3C West Forced Drainage
Project. The contractor has completed
the second lift of the new levee located on the west side of the island. The contractor is remobilizing to the east
side of the island in order to complete the project. The contractor is on schedule to complete the
project on time.
On
the Ward 7 Levee Reconstruction Project, Contracts 1 and 2 are both in clear
lien period. The contractor is currently
performing items on the punch list.
On
the Reach J-1 Levee and Floodwall project, Contract A contractor is preparing
for the second lift to onsite material.
The contractor is preparing to begin the final lift on the compacted
levee section. Work is progressing and
the contractor is on schedule. Contract
B is complete. The contractor has
completed planting marsh plants. On the
J-1 Floodwall, the construction contract is currently suspended. TBS is preparing a report to determine if a
10’ elevation can be handled by the pipeline.
If so, the existing contract will be terminated and a levee will be
constructed over the pipeline as part of J-1 Levee Contract A. TBS is working with Williams Pipeline to
provide a solution in order for the TLCD to construct the interim levee. TBS and TLCD representatives traveled to
On
the MTG Program Management Services contract, TBS worked on a crediting package
for Reach J-1. The is
the first crediting package to be submitted for the Morganza
Project. TBS also assisted the TLCD in
negotiating a Scope of Work to do the appraisals necessary for H-3. These appraisals should be complete in June
or July 2007.
Under
President’s Report, Mr. Alford reported on a meeting he attended with personnel
from LeBoeuf Brothers Towing.
There being no further
business to come before the Board, it was moved by Commissioner Leward Henry, seconded by Commissioner Moore, unanimously
carried, to adjourn the June 4, 2007 Planning & Projects Committee Meeting
of the Terrebonne Levee and Conservation District at 8:00 o’clock P.M.
________________________________
Walton
Daisy, Chairman
________________________________