Planning & Projects Meeting

April 7, 2008

 

 

Chairman Buddy Daisy called to order the Planning & Projects Committee Meeting of the Terrebonne Levee and Conservation District at the TLCD Office located at 220 Clendenning Road, Houma, Louisiana, on March 3, 2008, at 7:00 P.M..

 

Upon roll call by Angela Rains, Commissioners recorded present were Mr. Alford, Mr. Daisy, Ms. Dillard, Mr. Leward Henry, Mr. Willis Henry, Mr. Luke, Mr. Moore, Mr. Talbot and Ms. Teuton.

 

Under Public Wishing to address the Board, there was no one wishing to speak.

 

Under Executive Director’s Report, Mr. Zeringue discussed the Annual Inspection Trip and recommended scheduling the trip for May 12.  This item will appear on next week’s agenda for board action.

 

Mr. Zeringue presented the board with a cost estimate from T. Baker Smith to design the Forced Drainage 4-3C Terracing Mitigation Project.  The proposal is estimated to cost approximately $1.5 Million.  Several different mitigation alternatives have been evaluation.  This proposal is submitted for the board review.  If the TLCD scrubs the budget, approximately 1/3 to ˝ can be made available to begin this project.   The costs are much higher then originally anticipated due to post-Katrina inflation. 

 

Commissioner Alford suggested asking the Delegation for help in securing funding for mitigation projects, in light of the limited budget and future mitigation obligations.  Mr. Zeringue stated that the TLCD has up to two years to initiate this project.  Mr. Alford suggested that the TLCD obtain a five year extension due to lack of available funding to complete this project, and to give the Delegation time to work on securing additional funding. 

 

Mr. Phillip Chauvin urged the board to at least start some phase of this project, as the current time line has passed. 

 

This item is tabled until a future meeting. 

 

Mr. Zeringue asked for authorization to execute the Act of Servitude for the Chabert Property located along Upper Ward 7 Levee.

 

A motion was offered by Commissioner Leward Henry, seconded by Commissioner Luke, motion carried, to authorize the execution of the Act of Servitude for the Chabert property along Upper Ward 7 Levee. 

 

Mr. Zeringue requested permission to renew the Morganza Action Coalition membership in the amount of $20,000.00. 

 

A motion was offered by Commissioner Willis Henry, seconded by Commissioner Moore, motion carried, to renew the Morganza Action Coalition membership in the amount of $20,000.00.

 

Mr. Zeringue briefed the board on the Morganza to the Gulf Project.  A meeting was held with the State Delegation primarily to get support from the USACE to ensure the timeline established is meeting the goal.  The USACE is performing a reanalysis of the project cost estimate scheduled to be completed in July.  That report will be utilized to analyze the basis of the elevation height.  By the end of 2008, the access road will be constructed to begin the construction of the HNC Lock.  Secretary Woodley will travel to Houma for a stakeholder meeting scheduled for April 15, 2008.

 

Mr. Zeringue asked the board to deviate from the regular order of the agenda to address the Montegut Levee breach. 

 

A motion was offered by Commissioner Talbot, seconded by Commissioner Leward Henry, motion carried, to deviate from the regular order of the agenda to address the Montegut Levee breach.

 

A motion was offered by Commissioner Talbot, seconded by Commissioner Willis Henry, motion carried, to authorize the repair of the Montegut Levee breach with a not to exceed amount of $35,000.00.

 

A motion was offered by Commissioner Luke, seconded by Commissioner Alford, motion carried, to return to the regular order of the agenda.

  

Under Field Superintendent’s Report, Greg Gautreaux briefed the board on the ongoing in-house efforts to repair the Lower Ward 7 Levee.  The field crew completed hauling of the remaining 50,000 cubic yards of dirt.  Currently, there exists 1400-1500 cubic yards of material remaining to be placed on the levee. 

 

Bids for a super long reach excavator will be accepted Friday, April 11, 2008.

 

 

Planning & Projects Meeting

April 7, 2008

Page Two

 

 

A motion was offered by Commissioner Leward Henry, seconded by Commissioner Talbot, to award the bid for Borrow Material Only to The Merlin Group in the amount of $2.63 per yard.  After discussion, this motion was pulled and the agenda item was postponed until next week’s meeting.  The bid award for the Hauled Material was also pulled and postponed until next week’s meeting.

 

Mr. Gautreaux provided three quotes to blast and paint the TLCD spud barge and recommended awarding the bid to LeBouef Coatings, LLC in the amount of $27,454.00 for the work to be performed at the yard.

 

A motion was offered by Commissioner Talbot, seconded by Commissioner Willis Henry, motion carried, to award the bid to LeBouef Coatings, LLC in the amount of $27,454.00.

 

Mr. Gautreaux requested authorization to surplus one (1) 1982 International Dump Truck, one (1) 1998 Jeep Cherokee, and the sheet piling left from the Morganza to the Gulf Reach J-1 project.

 

A motion was offered by Commissioner Willis Henry, seconded by Commissioner Leward Henry, motion carried, to surplus the assets as requested. 

 

Mr. Keith Meyer with Evans-Graves Engineers, Inc. gave an update on the Pointe-Aux-Chenes Floodgate First Lift Levee System and the status of the Joint Permit Application.  The geotechnical department of the Corps has not finished the review of the plans and specifications.  In reference to the permit, the only outstanding issue is mitigation.  Approximately 3.1 acres will need to be mitigated at a total cost of $77,470.00.  Regarding utility relocation issues, drawings have been sent out to all utility companies impacted by the project.

 

Mr. Phil Schexnayder reported on the Reach J-2 project.  GSE submitted the Preliminary Plans and Specifications, as well as the 40% design document report last week to the TLCD.  It is currently being reviewed by the USACE, DOTD, and TLCD Staff. 

 

Mr. Jim Geihsler with Shaw Coastal, Inc. presented the board with a slide presentation on the Upper Ward 7 Levee.  Change Order No. 8 for this project has been deferred until the Regular Committee Meeting April 14, 2008.

 

Mr. Hilary Thibodeaux with Shaw Coastal, Inc. presented the Board with a slide presentation and update on Reach H-3 First Lift Project and the Permitting for Reach H.

 

Mr. Philip Chauvin of T. Baker Smith gave an update on Reach J-1 of the Morganza Project and Program Manager Services.  On the J-1 Levee Contract A, the contractor notified TBS on April 1, 2008 that the uncompacted portion of the levee is ready for compliance cross sections.

 

Under President’s Report, Mr. Alford thanked Councilman Joey Cehan for attending the meeting.  Mr. Alford provided a review of things working on.  Mr. Alford noted that Mr. Zeringue has been in contact with the USACE to find out what the future plans are to move ahead.  On the interim levee system, several possibilities have been explored for soil material.  Mr. Alford assured everyone that the TLCD board is looking at every alternative available to expedite the interim levee protection projects within the parish. 

 

There being no further business to come before the Board, it was moved by Commissioner Leward Henry, seconded by Commissioner Luke, unanimously carried, to adjourn the April 7, 2008 Planning & Projects Committee Meeting of the Terrebonne Levee and Conservation District at 7:56: o’clock P.M.

 

 

 

________________________________       

Walton Daisy, Chairman

 

 

 

________________________________       

Jerome Zeringue, Secretary