Planning
& Projects Meeting
Chairman
Upon
roll call by
Under
Public, there was no one wishing to address the board.
Under
Executive Director’s Report, Mr. Zeringue discussed the proposal to evaluate
the Environmental Water Control Structure for the Houma Navigation Canal
Interim Storm Protection. He requested
that a contract be entered into with Terrebonne Parish in the amount of
$20,000.00.
A
motion was offered by Commissioner Moore, seconded by Commissioner Willis Henry,
motion carried, to authorize the TLCD to enter into an agreement with
Terrebonne Parish in the amount of $20,000.00.
Mr.
Zeringue briefed the Board on a WRDA update for the Morganza to the Gulf
Hurricane Protection Project. President
Bush vetoed the WRDA bill and all indication is that the state and federal
delegation will override this veto and he feels confident that this bill will
be passed.
Field
Superintendent Greg Gautreaux provided an update of in-house projects along
Lower Ward 7 Levee. To date, the staff
has placed 33,000 cubic yards, with approximately 10,000 yards stockpiled at
Mr.
Zeringue asked the board to approve contract J-L-002C for GSE Associates, Inc.
A motion
was offered by Commissioner Moore, seconded by Commissioner Talbot, to
authorize the execution of the J-L-002C with GSE for the Reach J-2 Project,
subject to review by TLCD Board Attorney James Dagate.
Mark
Acosta with
Mr.
Zeringue asked the board to approve Amendment No. 7 to MPH-04 in the amount of
$9,150.00 for preparation of title opinions for the affected land in Lafourche
Parish.
A
motion was offered by Commissioner Willis Henry, seconded by Commissioner
Talbot, motion carried, to approve Amendment No. 7 to MPH-04 in the amount of
$9,150.00 for preparation of title opinions for the affected land in Lafourche
Parish.
Mr.
Pena presented the Board with a slide presentation and update on Reach H-3
First Lift Project and the Permitting for Reach H-3.
On
the Ward 7 Levee Project Inspection for the Lashbrook
Pump Station to Bayou Neuf Pump Station, the
contractor indicated he would not have completed that portion of the project by
the
Planning & Projects Meeting
Page Two
David
Boudreaux with T. Baker Smith, Inc. reported on the 4-3C West Forced Drainage
Project. He requested permission to
authorize Consolidated Waterworks District No. 1 to lower an asbestos concrete
waterline at a cost of $6,694.00.
A
motion was offered by Commissioner Willis Henry, seconded by Commissioner
Talbot, motion carried, to authorize Consolidated Waterworks District No. 1 to
lower an asbestos concrete waterline at a cost of $6,694.00.
Mr.
Boudreaux requested approval of Change Order No. 4 for a decrease of $49,492.14
for the 4-3C West Project. The
contractor has had a significant under run and there is not a need to haul in
as much dirt. Extra culverts were added
to allow more water to flow to the pump station, and still have a reduction of
$49,000.00.
A
motion was offered by Commissioner Talbot, seconded by Commissioner Luke,
motion carried, to approve Change Order No. 4 for a decrease of $49,492.14 for
the 4-3C West Project.
Mr.
Boudreaux asked for the acceptance of the Substantial Completion and Punch List
Approval for the 4-3C West Project. On
October 3, a substantial completion site visit was held and T. Baker Smith
accepted this project as substantially complete. As of this date, there is a 95% completion.
A
motion was offered by Commissioner Teuton, seconded by Commissioner Moore,
motion carried, to accept the Substantial Completion and Punch List for the
4-3C West Project.
In
regards to the Lower Ward 7 5-1A Project, T. Baker Smith,
Inc. provided a report that shows the important dates for this project, with an
amount that can be assessed for liquidated damages on Civil Construction Contractors
for being in default of the contract.
Mr.
Boudreaux asked for approval of Engineering Amendment No. 1 in the amount of
$22,420.50 for costs incurred by T. Baker Smith from time overruns on the Lower
Ward 7 Project. These overruns would be
paid from any potential liquidated damages against Civil.
Commissioner
Luke asked Board Attorney
Mr.
Boudreaux reported on the Reach J-1 Levee Project. He reported that the actual completion time
of Low Land Construction is
Under
President’s Report, Mr. Alford was absent.
There being no further
business to come before the Board, it was moved by Commissioner Leward Henry, seconded by Commissioner Talbot, motion
carried, to adjourn the November 5, 2007 Planning & Projects Committee
Meeting of the Terrebonne Levee and Conservation District at 7:30 o’clock P.M.
________________________________
Walton
Daisy, Chairman
________________________________