A
meeting of the Planning & Projects Committee of the Board of
1.
Meeting called to
order
2.
Roll Call
3. Public Wishing to Address the Board
4. Executive Director’s Report
a) Gulf South Pipeline – Reimbursement Agreement
with the Terrebonne Levee and Conservation District for Reach H-3 Morganza to
the Gulf Project
b) Eustis Engineering Revised Cost Proposal Reach
H Segment 3 – Task Order Eustis-07 – in the amount of $11,440.00
c) Resolution No. 07-433 - Authorizing Board
President
d) Morganza
to the Gulf – Update
5.
Field
Superintendent’s Report
a) In-house
Projects and Equipment – Update
6.
Engineer’s Report
a) Evans-Graves Engineers, Inc.
1) MTG
Bayou Pointe-Aux-Chene First Life Levee System Project – Update
b) GSE Associates, Inc.
1) Morganza to the Gulf – Reach J Segment 2 –
Update
c) Morris
P. Hebert, Inc.
1) Lower Petit Caillou
Levee Reconstruction Project (TE-07b) - Update
2) Morganza to the
Gulf Hurricane Protection Project
a)
Pointe-Aux-Chenes Floodgate - Update
b)
Bayou Pointe-Aux-Chenes First Lift Levee System – Update
d) Shaw
Coastal, Inc.
1) SCI
Project No. 1624 – Barrier Plan - Bayou Black Levee and Pump Station - Reach II
2) SCI Project No.
120942 & 125203 – Ward 7 Levee – Engineering and Construction
a) Contractor’s Change Order
Request for Additional Time Only
3) SCI
Project No. 123771 – Reach H, Segment 3, First Lift (H-L-003)
4) SCI Project No.
111838 – Morganza to the Gulf, Reach H Permitting
5) SCI Project No.
111837 – Lower Bayou Dularge Mitigation Plan Implementation
e) T. Baker Smith & Son,
Inc.
1) TBS Project No.
2004.0030 - Forced Drainage Project – 4-3C West - Project Update
2) TBS
Project No. 2001.0056 - Morganza Reach J-1 Levee – Contract A - Project Update
3) TBS
Project No. 2007.1121 - Morganza Program Management Services – Project Update
7.
President’s
Report
8.
Adjourn ________________________
Jerome
P. Zeringue, Secretary